Titan Series Commercial Ramp System Installation Manual Manufactured in the USA
– 10 – 2.5.1 Ramp must be positioned to one side or the other of the platform and should always be positioned to the outside of the turn. 2.5.2 Posi
– 11 – 4. INSTALLING SUPPORT LEGS TO RAMP SECTION(S): 4.1 Install leg support brackets and support legs to ramp section(s) as shown in FIG. 17. Note
– 12 – 4.13 The lowest ramp run will always begin with a starter section. This section requires the same installation procedure with two exceptions.
– 13 – 5. INSTALLING PLATFORM GUARDS: 5.1 Depending on the system configuration, following are four platform guardrail component options that may be
– 14 – 5.2 There are three basic platform arrangements: turn, turn-back, and straight through. Select appropriate guardrail installation and assemble
– 15 – 5.7 If platforms are being used to create a deck the entire outer edge of the deck must be guarded. 5.7.1 Installation of the guards at a cor
– 16 – 6. INSTALLING RAMP GUARDS: 6.1 Ramp guards come in left and right pairs and are not interchangeable from side-to-side. For all ramp sections
– 17 – 7. INSTALLING HANDRAILS: 7.1 Ramp handrails are supplied in left and right pairs and are not interchangeable. 7.1.1 Starting at the lower en
– 18 – 8.2 At the bottom of the ramp (i.e., ground), install two lower loops into the ends of each handrail (FIG. 34). 8.2.1 Install upper portion o
– 19 – 8.4 At a turn platform on the outside, non-turn side (both where a the top of a ramp meets a platform and where a ramp starts at a platform) a
– 2 – IMPORTANT! Read and follow all labels and assembly instructions – including warnings and cautions – prior to ramp use! INSPECTION (BEFORE USE):
– 20 – 8.6 At a turn-back platform on the inside, turn-back side (FIG. 37): 8.6.1 Hold two 90 degree elbows in position and mark for trimming. 8.6.2
– 21 – 8.7 At an intermediate turn platform on an inside corner (FIG. 39): 8.7.1 Hold two 90 degree elbows in position with the adjustable elbow and
– 22 – 8.8 When child rails are required, the lower (child) handrails and the various returns and connectors are installed in the same manner as the
– 23 – NOTES: Thank you for choosing Please visit www.ezaccess.com or call 1-800-258-8503 for all your ramp and step needs.
10257 REV 06-19-13 © EZ-ACCESS®, a division of Homecare Products, Inc. All rights reserved. All text and images contained in this document are propri
– 3 – TABLE OF CONTENTS BEFORE YOU BEGIN... 2 TOOLS NEEDED ...
– 4 – BEFORE YOU BEGIN: 1. Read and follow all instructions/warnings prior to assembly and use. 2. Load rating: 100 lbs. psf live load, 300 lbs. conc
– 5 – 1.5 Platforms over 3 ft. high from the ground require cross bracing. 1.5.1 Insert legs into platform and set platform at required height as de
– 6 – FIG. 5 FIG. 6 1.7 Platforms can also be combined in any direction in multiples of 64-7/16” to create a deck. The initial steps are similar
– 7 – 1.7.6 In all locations where there will be no guards or filler sections install the 1-1/2” square x 11” long tube provided through the platform
– 8 – FIG. 9 FIG. 10 FIG. 11 FIG. 12
– 9 – 2. ASSEMBLE/SET RAMPS: 2.1 Begin setting ramps with the uppermost ramps in the system. 2.2 There are three different bracket types that are u